Kaniv Hydroelectric Power Plant
Reconstruction of the electrical part and hydro units, installation and commissioning of equipment.
- Type
- MODERNIZATION
- Status
- reference
- Years
- 2012–2021
- Location
- Ukraina / Ukraine
- Role
- Reconstruction & installation
Project gallery
Comprehensive modernization delivered in several stages: reconstruction of the electrical part of unit No. 6 (2012–2013); reconstruction of hydro units No. 2 and 3 — 8 generating sets (2014–2016) with replacement of electrical and hydraulic equipment and a new control system; installation and commissioning of two further units — 7 turbines and 7 generators together with Ukrainian Energy Machines (2017–2021); building repair works, deformation-seam repairs and replacement of the T4 power transformer.
Scope of works
- reconstruction of hydro units No. 2, 3 and 6
- new control system
- installation of 7 turbines and 7 generators
- T4 transformer replacement